Site Work and Grading Contractor
Serving Anderson, SC
Clearing, mass grading, building pads, erosion control and storm drainage for commercial and industrial sites in Anderson and Anderson County, under RO Unlimited's own South Carolina grading license. Anderson County splits site approval into two permits from two departments, and adds a stream buffer wider than most.
Moving Dirt in Anderson County
Two permits, two departments
Anderson County requires a stormwater permit for land disturbing activity of one acre or more, and its Stormwater Department has 20 working days to review a plan. That is four weeks on the calendar for the first review alone, before any comments are answered.
The grading permit is not part of it. The county's own flow chart notes that the grading permit must be obtained from the Development Standards Department by separate application. The stormwater approval, the stamped plans and the grading permit are then handed over together at the pre-construction meeting. We file the two applications side by side so one is not waiting on the other.
Buffers of 50 to 100 feet
Anderson County adopted a riparian buffer ordinance, Ordinance 2025-018, that sets a buffer of 50 to 100 feet from all waters of the state. In a county that borders Lake Hartwell and is cut by creeks running to it, that takes real ground out of a site plan.
A buffer that wide can move a pad, a detention pond or a driveway, and it has to be flagged in the field before clearing so an operator does not cross it. If your survey shows a stream or a wet-weather draw, the buffer should be on the first sketch, not discovered at plan review.
City sites and small sites
Inside the City of Anderson the reviewer changes. The city owns and operates its own small municipal storm sewer system, has its own land development regulations for plan review, and SCDES lists the city's Building Department as the reviewing entity. Incorporated towns in the county that are not listed by SCDES send their plans to the state's Bureau of Water instead.
State coverage comes under SCDES Construction General Permit SCR100000 at one acre or more, or for smaller lots in a larger common plan. Below an acre, SCDES says you must still complete a form, though you do not need a permit.
Big pads on Piedmont clay
With over 30 miles of I-85 frontage, Anderson County sees a lot of large industrial pads. The ground under them is typically Piedmont upland soil of the kind the USDA describes in the Cecil series: very deep, red clay in the subsoil, saprolite beneath, formed from weathered igneous and metamorphic rock.
On a large pad the work is in the numbers. Tens of thousands of cubic yards have to balance between cut and fill, every lift of fill is tested for density, and the finished subgrade has to carry truck traffic. Clay that is too wet will not reach density however many passes it gets, so we plan drying and proof-rolling time into the job.
Who Signs Off in Anderson
Anderson County Stormwater Department
Permit for one acre or more of land disturbance; 20 working days to review a plan. Riparian buffers of 50 to 100 feet.
Anderson County Development Standards
Separate application from the stormwater permit; delivered with it at the pre-construction meeting.
City of Anderson Stormwater Management
The city runs its own storm sewer system and land development regulations for plan review.
SCDES Bureau of Water
Construction General Permit SCR100000. Lists which local office reviews plans in each jurisdiction.
Agency names and requirements are taken from each agency's own published pages. They change, so the permit path for your parcel is confirmed with the agency before we price it.
The Work, Up Close



Licensed from raw land to pad
Grading, roads and parking, concrete, and the water and sewer lines that go in before the pad is finished, all under our own South Carolina license classifications.
Grading
Clearing and grubbing, mass excavation, embankment, building pads, site balancing and finish grading.
Water & Sewer Lines
Water mains, taps and services, sanitary sewer, storm drainage, force mains and lift stations.
Concrete
Footings, foundations, structural slabs, walls, curb and gutter, sidewalks and concrete paving.
Highway
Roads, streets, parking lots, bridges and the incidental structures that go with them.
Asked Before the Bid
How long does Anderson County take to review a stormwater plan?
The county's Stormwater Department states it has 20 working days to review a plan for land disturbing activity of one acre or more. The grading permit is a separate application to the Development Standards Department.
How close to a creek can I grade in Anderson County?
Anderson County's riparian buffer ordinance, Ordinance 2025-018, sets a buffer of 50 to 100 feet from all waters of the state. The width that applies to your stream is confirmed with the county at plan review.
Do I need a permit to grade less than an acre in Anderson?
At the state level, SCDES says that for land disturbance of less than one acre you must complete a form but do not need a permit, unless the lot is part of a larger common plan. City and county requirements can still apply, so we check with the reviewing office for the parcel.
Can RO handle the storm drainage as well as the grading?
Yes. RO Unlimited holds South Carolina classifications for grading and for water and sewer lines, which covers storm drainage, along with concrete and highway work for curbs, parking and drives.
More From RO Unlimited
Site Work & Grading in nearby towns
Send Us
Your Plans
Send the civil set or the survey for your Anderson site. We will tell you which permits it needs, where the buffers fall and what the dirt work involves.
(864) 304-0139