RO Unlimited builds commercial buildings and does the site work under them across the Savannah River in Northeast Georgia: Stephens, Franklin and Hart counties. We are licensed as a general contractor in Georgia as well as South Carolina. The rules for moving dirt change at the state line, and this page covers how.
Building in Northeast Georgia
Who issues the land disturbance permit
Georgia lets a city or county be certified as a Local Issuing Authority and issue its own land disturbance permits. On the Georgia Environmental Protection Division's August 2025 list, the City of Toccoa is certified. Stephens County, Franklin County, the City of Lavonia, Hart County and the City of Hartwell are not.
Where there is no local authority, the erosion control plan goes to EPD itself: one copy to the Watershed Protection Branch and one to the district office, which for all three counties is the Northeast District in Athens. So a site inside Toccoa and a site five miles outside it follow different paths.
The state permit and its 14 days
Sites that disturb one acre or more need coverage under one of Georgia's construction stormwater general permits: GAR100001 for a stand-alone project, GAR100002 for infrastructure, GAR100003 for a common development. The current permits took effect on August 1, 2023 and run to July 31, 2028.
The Notice of Intent has to be filed at least 14 days before construction starts, through EPD's online system. Franklin County's own permit checklist asks for that notice with the application when grading exceeds an acre. Georgia 811 asks for at least three business days' notice before digging.
Buffers and certified people on site
Georgia's permit bars construction within a 25 foot buffer along the banks of all state waters, and within 50 feet on waters classed as trout streams. The buffer is measured from where the stream has wrested the vegetation, not from the property line.
The state also regulates who is on the job. Each permittee needs at least one person in responsible charge of erosion control who holds the Georgia Soil and Water Conservation Commission's Level IA certification, the card Stephens and Franklin counties both ask to see. Certified personnel must inspect the site at least twice every seven days.
Water, sewer and gas by town
Toccoa draws its water mainly from Lake Toccoa, supplemented from Davidson Creek and Lake Yonah, and also runs Toccoa Natural Gas, a regional system reaching Stephens, Franklin and Hart counties. New commercial service starts with the city's tap applications. Hartwell withdraws from Lake Hartwell, treats up to 4.5 million gallons a day, and upgraded its sewer plant in 2025 for industrial loadings.
Outside Hartwell, the Hart County Water and Sewer Authority serves the unincorporated county, including sewer customers at Gateway Park near I-85. Franklin County's water system runs on groundwater wells. In Lavonia we confirm the provider and the tap process with the city for each site.
Licensing differs from South Carolina
Georgia requires a license to perform commercial general contracting, and RO's Georgia general contractor license number is furnished with any bid or prequalification package.
Georgia also licenses utility contracting on its own. State board rules define it as work on utility systems at least five feet underground, and the Hart County Water and Sewer Authority requires any contractor connecting to its system to hold a Georgia utility contractor's license. On a Georgia project we set out in the proposal which license each part of the work is performed under.
What is being built here
The I-85 corridor through these counties is drawing large projects. In August 2026 the Governor's office announced a 1.5 million square foot Walmart fulfillment center at the Franklin 85 Logistics Center in Carnesville, a $1.3 billion investment. Hart County's Gateway Industrial Park sits at Exit 177, and Nestlé Purina committed $550 million to expanding its Hartwell plant in 2020.
In Toccoa, the Stephens County Development Authority's Hayestone Brady Business Park has about 100 acres left with pad-ready certified sites. The ground is rolling Piedmont: Hart County's plan names Madison sandy loam as its most common soil, a mica-rich soil over weathered schist that needs care to compact.
Who Signs Off in Northeast Georgia
City of Toccoa (Local Issuing Authority)
The only certified Local Issuing Authority among these cities and counties on the EPD list of August 2025.
Georgia EPD, Northeast District (Athens)
Receives erosion control plans where there is no Local Issuing Authority. Notice of Intent 14 days before construction.
Stephens County Building Department
Asks for the Level IA erosion control certification where it applies.
Franklin County Building Department
Issues permits and enforces erosion and sediment controls for new development in the county.
Hart County Building Permitting Office
Building permits in the unincorporated areas of Hart County.
Hart County Water and Sewer Authority
Written approval required before connecting; contractor must hold a Georgia utility contractor license.
Agency names and requirements are taken from each agency's own published pages. They change, so the permit path for your parcel is confirmed with the agency before we price it.
The Work, Up Close



Licensed on both sides of the river
RO holds a Georgia general contractor license, furnished with any bid or prequalification package, alongside the South Carolina classifications below.
Building
Commercial, industrial, institutional and multi-family buildings — ground-up, shells, build-outs and additions.
Grading
Clearing and grubbing, mass excavation, embankment, building pads, site balancing and finish grading.
Water & Sewer Lines
Water mains, taps and services, sanitary sewer, storm drainage, force mains and lift stations.
Concrete
Footings, foundations, structural slabs, walls, curb and gutter, sidewalks and concrete paving.
Asked Before the Bid
Who issues land disturbance permits in Toccoa, Lavonia and Hartwell?
On the Georgia EPD list updated in August 2025, the City of Toccoa is a certified Local Issuing Authority and issues its own. Stephens County, Franklin County, Lavonia, Hart County and Hartwell are not certified, so erosion control plans there are submitted to Georgia EPD and its Northeast District office in Athens.
How far ahead must a Notice of Intent be filed in Georgia?
At least 14 days before construction activity begins, for sites disturbing one acre or more. It is filed electronically with Georgia EPD under general permit GAR100001, GAR100002 or GAR100003, depending on the type of project.
How close to a stream can we build in Northeast Georgia?
Georgia's construction stormwater permit prohibits construction within a 25 foot buffer along the banks of state waters, and within 50 feet along trout streams, measured from the point where stream flow has wrested the vegetation.
Is RO Unlimited licensed to build in Georgia?
Yes. RO Unlimited holds a Georgia general contractor license in addition to its South Carolina licenses. The Georgia license number is furnished with any bid or prequalification package. We serve Northeast Georgia from the Upstate and have no office there.
More From RO Unlimited
Commercial Construction & Site Work in nearby towns
Send Us
Your Plans
Send the plans or the site address in Stephens, Franklin or Hart County. We will tell you who issues the permits, who supplies the utilities and what the work involves.
(864) 304-0139